  • AIRSIDE LOGISTICS RELOCATION PROJECT

    Airside Logistics New Facilities

     

    (Quick Facts)
    Project Name: Airside Logistics New Facilities
    Project Location: Mount Isa Airport Aviation Precinct
    Project Cost: 1.8M
    Date of Completion: October 2012
    Duration: 22 Weeks

    Project Scope:

    Design and Construct of a freight forwarding facility located in Mount Isa and supply and service corridor and upgrade the fire ring mains of the terminal.

    Project Challenges:

    Remote area works involve a high level of pre-planning for the resource delivery and logistical time frames.

    Project Delivery:

    This project had a 1-month delay due to the late delivery of a specialized internal wall panel

    Read more

    TAPL ASSET AND SAFETY BUILDING PROJECT

    (Quick Facts)

    Project: Safety & Asset Building
    Client: Townsville Airport Ltd
    Description: Construction of new Safety and Asset maintenance facility
    Location: Garbutt, Townsville

    Project Value: $1 Million

    Read more

    TAPL SHADE STRUCTURE PROJECT

    (Quick Facts)
    Project Name: TAPL SHADE STRUCTURE PROJECT
    Project Location: Townsville Airport
    Project Cost:  2.2 Million
    Date of Completion:
    Duration: March 2016

    Project Scope:

    Furthering and extending the Shaded Structures at Front of Terminal for the Short Term Car Park Facility’s at Townsville International Airport Facility. 4 More bays are to be added to the first stage of this project from 2014. a total of 2500m2 will be added to enhance the customers experience while utilising the airports facilities for short term drop of and pick ups. 
     
    These works are schedule for a 4-5 Week construction time frame. with 2 months of carefully planning site establishment and the material logistics in and out of site with more then 2000 Cars per day up to 4000 Passengers in close proximity to construction activities. 

     

     

    Read more

    CLONCURRY AIRPORT UPGRADE PROJECT

    Project Name: CLONCURRY AIRPORT REDEVELOPMENT
    Project Location: Sir Hudson Fysh Drive, CLONCURRY
    Project Cost: $3.3 Million
    Date of Completion: MAY 2016­ 02­ 09
    Project Duration: 10 Months
    Project Scope: Enlarge and refurbish existing Sterile departure Lounge and toilets.
    ­Build a 586M2 Extension to house Passenger and Check Bag screening, Check­in
    Counters , Baggage Claim , Toilets and facilities.

    ­Covered Awning area for Pickup , Set down and Baggage area
    ­ New Electrical Infrastructure Building Services
    ­ New Air Conditioning and Ventilation system

    Project Challenges:
    ­ Traffic management for scheduled flights
    ­ Manage Access for continued pedestrian movement ­ Security issues associated with Airside access – 5 staff with ASIC cards
    ­ Specially designed Online Safety Induction
    ­ Hidden and undocumented Services and infrastructure

     

    Read more

    RELOCATION TAXI RANK TAPL

    RELOCATION TAXI RANK TAPL

    (Quick Facts)
    Project Name: RELOCATION TAXI RANK TAPL
    Project Location: Townsville Airport Terminal
    Project Cost: $200,000
    Date of Completion: Dec 2007
    Duration: 2 Weeks

    Job Scope:

    Supply and install demountable crib room facilities for the Taxi drivers set down area at the Townsville airport

    Project Challenges:

    Nil

    Read more

    TOWNSVILLE ROYAL FLYING DOCTORS CARPARK

    Royal Flying Doctors Services

    (Quick Facts)
    Project Name: Royal Flying Doctors Services
    Project Location: Townsville Airport Aviation Precinct
    Project Cost: $120,000
    Date of Completion: Feb 2010
    Duration: 4 Weeks
    Read more

    TAPL FOT REJUVENATION PROJECT

    FOT Rejuvenation Project

    (Quick Facts)
    Project Name: FOT Rejuvenation Project
    Project Location: Townsville Airport Terminal
    Project Cost: $200,000
    Date of Completion: Dec 2014
    Duration: 8 Weeks

     

    Project Scope:

    Remove sections of gardens located at the Front of Terminal and replace with new plants to rejuvenate dated garden beds.  Supply and erect architectural steel feature frames to the front facade for climbing plants feature to enhance the look of the domestic terminal.

    Project Challenges:

    All these works have to be performed during the day night to eliminate the chance of disturbing the airports daily operations. Core only has a 6-hour window each night to perform these scheduled works

    Project Delivery:

    This project was delivered on time and in budget.

    Read more

    MOUNT ISA AIRPORT CAFE

     Pat Rafter Café

     

    (Quick Facts)
    Project Name: Pat Rafter Café
    Project Location: Mount Isa Airport Terminal
    Project Cost: $310,000
    Date of Completion: June 2011
    Duration: 12 Weeks

    Project Scope:

    Demolitions of old Café and construction of new facilities

    Project Challenges:

    This project was set up in Townsville the week before cyclone YASI, and all materials and labor were repacked and delivered to the rural site before the tropical category 2 storm hit. This was the first crisis management situation Core Developments NQ Pty Ltd endured./managed.

    Project Delivery:

    This project was delivered 2 weeks early due to mobilizing site early to avoid storm damage. May we never forget the power of a Category 2 cyclone

    Read more