AIRSIDE LOGISTICS RELOCATION PROJECT

Airside Logistics New Facilities

 

(Quick Facts)
Project Name: Airside Logistics New Facilities
Project Location: Mount Isa Airport Aviation Precinct
Project Cost: 1.8M
Date of Completion: October 2012
Duration: 22 Weeks

Project Scope:

Design and Construct of a freight forwarding facility located in Mount Isa and supply and service corridor and upgrade the fire ring mains of the terminal.

Project Challenges:

Remote area works involve a high level of pre-planning for the resource delivery and logistical time frames.

Project Delivery:

This project had a 1-month delay due to the late delivery of a specialized internal wall panel

Read more

TAPL ASSET AND SAFETY BUILDING PROJECT

(Quick Facts)

Project: Safety & Asset Building
Client: Townsville Airport Ltd
Description: Construction of new Safety and Asset maintenance facility
Location: Garbutt, Townsville

Project Value: $1 Million

Read more

TAPL SHADE STRUCTURE PROJECT

(Quick Facts)
Project Name: TAPL SHADE STRUCTURE PROJECT
Project Location: Townsville Airport
Project Cost:  2.2 Million
Date of Completion:
Duration: March 2016

Project Scope:

Furthering and extending the Shaded Structures at Front of Terminal for the Short Term Car Park Facility’s at Townsville International Airport Facility. 4 More bays are to be added to the first stage of this project from 2014. a total of 2500m2 will be added to enhance the customers experience while utilising the airports facilities for short term drop of and pick ups. 
 
These works are schedule for a 4-5 Week construction time frame. with 2 months of carefully planning site establishment and the material logistics in and out of site with more then 2000 Cars per day up to 4000 Passengers in close proximity to construction activities. 

 

 

Read more

CLONCURRY AIRPORT UPGRADE PROJECT

Project Name: CLONCURRY AIRPORT REDEVELOPMENT
Project Location: Sir Hudson Fysh Drive, CLONCURRY
Project Cost: $3.3 Million
Date of Completion: MAY 2016­ 02­ 09
Project Duration: 10 Months
Project Scope: Enlarge and refurbish existing Sterile departure Lounge and toilets.
­Build a 586M2 Extension to house Passenger and Check Bag screening, Check­in
Counters , Baggage Claim , Toilets and facilities.

­Covered Awning area for Pickup , Set down and Baggage area
­ New Electrical Infrastructure Building Services
­ New Air Conditioning and Ventilation system

Project Challenges:
­ Traffic management for scheduled flights
­ Manage Access for continued pedestrian movement ­ Security issues associated with Airside access – 5 staff with ASIC cards
­ Specially designed Online Safety Induction
­ Hidden and undocumented Services and infrastructure

 

Read more

RELOCATION TAXI RANK TAPL

RELOCATION TAXI RANK TAPL

(Quick Facts)
Project Name: RELOCATION TAXI RANK TAPL
Project Location: Townsville Airport Terminal
Project Cost: $200,000
Date of Completion: Dec 2007
Duration: 2 Weeks

Job Scope:

Supply and install demountable crib room facilities for the Taxi drivers set down area at the Townsville airport

Project Challenges:

Nil

Read more

TOWNSVILLE ROYAL FLYING DOCTORS CARPARK

Royal Flying Doctors Services

(Quick Facts)
Project Name: Royal Flying Doctors Services
Project Location: Townsville Airport Aviation Precinct
Project Cost: $120,000
Date of Completion: Feb 2010
Duration: 4 Weeks
Read more

TAPL FOT REJUVENATION PROJECT

FOT Rejuvenation Project

(Quick Facts)
Project Name: FOT Rejuvenation Project
Project Location: Townsville Airport Terminal
Project Cost: $200,000
Date of Completion: Dec 2014
Duration: 8 Weeks

 

Project Scope:

Remove sections of gardens located at the Front of Terminal and replace with new plants to rejuvenate dated garden beds.  Supply and erect architectural steel feature frames to the front facade for climbing plants feature to enhance the look of the domestic terminal.

Project Challenges:

All these works have to be performed during the day night to eliminate the chance of disturbing the airports daily operations. Core only has a 6-hour window each night to perform these scheduled works

Project Delivery:

This project was delivered on time and in budget.

Read more

MOUNT ISA AIRPORT CAFE

 Pat Rafter Café

 

(Quick Facts)
Project Name: Pat Rafter Café
Project Location: Mount Isa Airport Terminal
Project Cost: $310,000
Date of Completion: June 2011
Duration: 12 Weeks

Project Scope:

Demolitions of old Café and construction of new facilities

Project Challenges:

This project was set up in Townsville the week before cyclone YASI, and all materials and labor were repacked and delivered to the rural site before the tropical category 2 storm hit. This was the first crisis management situation Core Developments NQ Pty Ltd endured./managed.

Project Delivery:

This project was delivered 2 weeks early due to mobilizing site early to avoid storm damage. May we never forget the power of a Category 2 cyclone

Read more