AIRSIDE LOGISTICS RELOCATION PROJECT

Airside Logistics New Facilities

 

(Quick Facts)
Project Name: Airside Logistics New Facilities
Project Location: Mount Isa Airport Aviation Precinct
Project Cost: 1.8M
Date of Completion: October 2012
Duration: 22 Weeks

Project Scope:

Design and Construct of a freight forwarding facility located in Mount Isa and supply and service corridor and upgrade the fire ring mains of the terminal.

Project Challenges:

Remote area works involve a high level of pre-planning for the resource delivery and logistical time frames.

Project Delivery:

This project had a 1-month delay due to the late delivery of a specialized internal wall panel