Project Name: CLONCURRY AIRPORT REDEVELOPMENT
Project Location: Sir Hudson Fysh Drive, CLONCURRY
Project Cost: $3.3 Million
Date of Completion: MAY 2016 02 09
Project Duration: 10 Months
Project Scope: Enlarge and refurbish existing Sterile departure Lounge and toilets.
Build a 586M2 Extension to house Passenger and Check Bag screening, Checkin
Counters , Baggage Claim , Toilets and facilities.
Covered Awning area for Pickup , Set down and Baggage area
New Electrical Infrastructure Building Services
New Air Conditioning and Ventilation system
Project Challenges:
Traffic management for scheduled flights
Manage Access for continued pedestrian movement Security issues associated with Airside access – 5 staff with ASIC cards
Specially designed Online Safety Induction
Hidden and undocumented Services and infrastructure