Under Construction Office Fit Out

Project Name: Core Developments New Offices Warehouse Refurbishment Stage 1
Project Location: 327 Ingham Road
Due for Completion: Aug 2024
Project Duration: 5 Months
Project Scope: Construction of a new Warehouse and realignment of the existing drive way

Project Challenges:

  • ­High level project staging and planning
  • ­Maintaining an operational environment for continued business operations
  • High exposed site on a main artillery road with very little set down area for preparation works
Read more

Under Construction New Warehouse

Project Name: Core Parts New Warehouse Stage 2
Project Location: 275 Ingham Road
Due for Completion: Aug 2024
Project Duration: 5 Months
Project Scope: Construction of a new Warehouse and realignment of the existing drive way

Project Challenges:

  • ­High level project staging and planning
  • ­Maintaining an operational environment for continued business operations
  • High exposed site on a main artillery road with very little set down area for preparation works
  • Storm water drainage with limited run off

 

Read more

AMENITIES UPGRADE PROJECT

Project Name: Amenities Upgrade Project
Project Location: Townsville Airport – Domestic Terminal
Date of Completion: Nov 2022
Project Duration: 4 Months
Project Scope: Design and construction of new Amenities female, male, PWD, Parents Room and a certified changing place facility adult changing facility

Project Challenges:

­High level project staging and planning
­Maintaining an operational environment for continued passenger movement ­through the terminal whilst coordinating construction elements in order to meet the client desired completion targets.

Read more

QPWS MAGNETIC ISLAND BASE EXPANSION

Project Name: QPWS MAGNETIC ISLAND BASE EXPANSION
Project Location: Hurst Street Magnetic Island, Picnic Bay
Project Cost: Between 500>1M
Date of Completion: 18/1/2019
Project Duration: 4 Months
Project Scope: Demolish existing office block, and re build new office and warehouse configuration.

Project challenges: Work’s commencing in wet season, and tight access to most external areas of the build.

 

Read more

WOONGARRA CREMATORIUM

 

Project Name: Morley’s Woongarra Crematorium
Project Location: Stuart QLD
Project Cost: Upon inquiry
Date of Completion: 30th June 2018
Project Duration: 6 Months
Project Scope: Renovate existing building with 200m² extension to accommodate new cremator and Viewing/Ceremony room as well as new drive-thru delivery point.

Project challenges: Long stand suspended deck to existing structure, ground slab supporting heavy point loads.

Working project around ceremonies without creating any disruptions in the form of excessive noise or essential services such as Water/Gas/Electricity.

Read more

275 INGHAM ROAD WAREHOUSE

Project Name: 275 INGHAM ROAD WAREHOUSE

Project Location: 275 Ingham Road, TOWNSVILLE

Project Cost: $450,000

Date of Completion: Oct 2016

Project Duration: 3 Months

Project Scope: Design and Construct 300mm2 Warehouse and office Mezzanine

Project Challenges: Building was build on property boundary making access for finishing difficult

Read more

AIRSIDE LOGISTICS RELOCATION PROJECT

Airside Logistics New Facilities

 

(Quick Facts)
Project Name: Airside Logistics New Facilities
Project Location: Mount Isa Airport Aviation Precinct
Project Cost: 1.8M
Date of Completion: October 2012
Duration: 22 Weeks

Project Scope:

Design and Construct of a freight forwarding facility located in Mount Isa and supply and service corridor and upgrade the fire ring mains of the terminal.

Project Challenges:

Remote area works involve a high level of pre-planning for the resource delivery and logistical time frames.

Project Delivery:

This project had a 1-month delay due to the late delivery of a specialized internal wall panel

Read more

2 UNIT WAREHOUSE TILT SLAB PROJECT

(Quick Facts)
Project Name:
2 UNIT WAREHOUSE TILT SLAB PROJECT
Project Location: 27 Cottell Street Hyde Park,
Project Cost:  approx. $860,000
Date of Completion: May 2009
Duration: 16 weeks

Project Scope:  
Design and Construct two concrete precast ware houses located in the CBD of Townsville.

Project Challenges: 
The challenges we endeavored on the project was managing the pour foundations of the subgrade and its location. And also building 50mm from the boundary allotment with very little lay down areas.

Project Delivery:  
This project was delivered 2 weeks late due to wet weather delays and logistic operation constraints. The contractors involved in this particular project made a great effort to make this delivery successfu

Read more