AIRSIDE LOGISTICS RELOCATION PROJECT

Airside Logistics New Facilities

 

(Quick Facts)
Project Name: Airside Logistics New Facilities
Project Location: Mount Isa Airport Aviation Precinct
Project Cost: 1.8M
Date of Completion: October 2012
Duration: 22 Weeks

Project Scope:

Design and Construct of a freight forwarding facility located in Mount Isa and supply and service corridor and upgrade the fire ring mains of the terminal.

Project Challenges:

Remote area works involve a high level of pre-planning for the resource delivery and logistical time frames.

Project Delivery:

This project had a 1-month delay due to the late delivery of a specialized internal wall panel

Read more

WEST END OFFICE COMPLEX PROJECT

Project Name: West End Office Complex
Location: Hermit Park
Cost: $350,000
Completion: July 2016
Project Scope:
To construct a two storey office building onto existing older single storey office building
Project Challenges:
This project was delivered during business hours in a high foot traffic location
Project Delivery:
project delivered on time and in budget.

Read more

MORLEY’S FUNERALS EXTENSION

Morleys Funerals

 

(Quick Facts)
Project Name: Morleys Funerals
Project Location: Morleys Funerals
Project Cost: 600,00 ongoing
Date of Completion:  Ongoing
Duration:  Ongoing

Project Scope:

Core Developments NQ is Proud to deliver the latest extension to Morley’s Funeral Parlour located in The Lakes Townsville. This schedule was completed in just less than 12 weeks. We would like the thank the contractors and design consultants that delivered this project during wet season.

Project Challenges:

Civil and foundation started in wet season, scheduling  work around funeral’s.

Project Delivery:

Project delivered on time and on budget.

Read more

CENTURY 21 OFFICE RELOCATION

Century 21 Offices

 

(Quick Facts)
Project Name: Century 21 Offices
Project Location: Kirwan Branch Townsville
Project Cost: $120,000
Date of Completion: May 2014
Duration: 4 Weeks

Project Scope:

Internal shop fit out for new business location

Project Challenges:

Core Developments was given a 4-week time frame to have this project ready before existing lease expired. Core worked around the clock and worked in with the client to achieve the desired results meeting the client’s needs.

Project Delivery:

This project was delivered on time and well under budget. Thank you to Aaron and Katrina for the full support during this project.

Read more

COFFEY RELOCATION PROJECT

Coffey Soil Testing Facility

(Quick Facts)
Project Name: Coffey Soil Testing Facility
Project Location: Industry Park 547 Townsville
Project Cost: $260,000
Date of Completion: Oct 2013
Duration: 12 Weeks

 

Project Scope:

Relocate Coffey’s operations in Townsville. Works included construction of a new facility and repair old tenancy to original state..

Project Challenges:

This project had a tight time frame for the transition period. Construction phase had to be sped up and more resources had to be allocated to this project during day and night.

Project Delivery:

This project was delivered on time and in budget

Read more

IPL PHOSPHATE HILL CAMP UPGRADE

 

IPL Mine Camp Upgrade Project

 

(Quick Facts)
Project Name: Camp upgrade IPL 216 Units
Project Location: The Monument Camp (Phosphate Hill)
Project Cost: 15.7M
Date of Completion: June 2013
Duration: 14 Months

Project Scope:

Demolish 40 houses and 6 SPQ, construct and build onsite 216 units in the monument camp facilities, each unit having its own bathroom and shower amenities.

Project Challenges:

This project was located in a remote community/township approximately 10 hours west of the east coast of Northern Australia.

During this project Core managed severe wind and wet weather events and many lightning storms resulting to a delay in the works and schedule.

Project Delivery

With over 130,000 personal hours on this project core successfully delivered this project with zero harm taking away the 2013 work safe awards for Queensland Core Developments delivered a high quality product fully furnished, achieving no loss time and medical treated injury during the construction and demolition periods.

Read more

MOUNT ISA AIRPORT CAFE

 Pat Rafter Café

 

(Quick Facts)
Project Name: Pat Rafter Café
Project Location: Mount Isa Airport Terminal
Project Cost: $310,000
Date of Completion: June 2011
Duration: 12 Weeks

Project Scope:

Demolitions of old Café and construction of new facilities

Project Challenges:

This project was set up in Townsville the week before cyclone YASI, and all materials and labor were repacked and delivered to the rural site before the tropical category 2 storm hit. This was the first crisis management situation Core Developments NQ Pty Ltd endured./managed.

Project Delivery:

This project was delivered 2 weeks early due to mobilizing site early to avoid storm damage. May we never forget the power of a Category 2 cyclone

Read more