Pat Rafter Café

 

(Quick Facts)
Project Name: Pat Rafter Café
Project Location: Mount Isa Airport Terminal
Project Cost: $310,000
Date of Completion: June 2011
Duration: 12 Weeks

Project Scope:

Demolitions of old Café and construction of new facilities

Project Challenges:

This project was set up in Townsville the week before cyclone YASI, and all materials and labor were repacked and delivered to the rural site before the tropical category 2 storm hit. This was the first crisis management situation Core Developments NQ Pty Ltd endured./managed.

Project Delivery:

This project was delivered 2 weeks early due to mobilizing site early to avoid storm damage. May we never forget the power of a Category 2 cyclone