Project Name: St Patrick College Soil Remediation Project
Project Location: Townsville The Strand
Project Cost: 500K – 1M
Date of Completion: July 2019
Duration: 4 week

Project Name: St Patrick College Soil Remediation Project
Project Location: Townsville The Strand
Project Cost: 500K – 1M
Date of Completion: July 2019
Duration: 4 week
TOWNSVILLE PORT SHED DEMO CONSULTING 2013
MT ISA DENTAL CLINIC DEMOLITION WORKS 2015
PALM ISLAND BUTLER BAY HOUSING 2015
WEIPA PORT DOLPHIN WHARF DEMO CONSULTING 2015
LEXUS TOWNSVILLE FIRE DAMAGE PANELS 2016
SHUTE HARBOUR JETTY DEMO CONSULTING 2017
LOVES JETTY DEMO CONSULTING 2017
(Quick Facts)
Project Name: TAPL Building Office Administration
Project Location: Garbutt, Townsville
Project Cost: approx. $210,000
Date of Completion: October 2014
Duration: 8 week
(Quick Facts)
Project Name: Demolition of Building 90
Project Location: Townsville Airport, Garbutt
Cost: approx. $200,000
Date of Completion: April 2017
Duration: 14 weeks
(Quick Facts)
Project Name: Phosphate Hill Camp Upgrade
Project Location: Phosphate Hill (50 Houses)
Project Cost: approx. $1,310,000
Date of Completion: April 2013
Duration: 12 Months
(Quick Facts)
Project Name: Demolition Tony Ireland used car yard
Project Location: Charters Towers Road
Project Cost: $150,000
Date of Completion: November 2011
Duration: 6 weeks