(Quick Facts)
Project Name: Demolition of Building 90
Project Location: Townsville Airport, Garbutt
Cost: approx. $200,000
Date of Completion: April 2017
Duration: 14 weeks
(Quick Facts)
Project Name: Demolition of Building 90
Project Location: Townsville Airport, Garbutt
Cost: approx. $200,000
Date of Completion: April 2017
Duration: 14 weeks
IPL Mine Camp Upgrade Project
(Quick Facts) | |
Project Name: | Camp upgrade IPL 216 Units |
Project Location: | The Monument Camp (Phosphate Hill) |
Project Cost: | 15.7M |
Date of Completion: | June 2013 |
Duration: | 14 Months |
Project Scope:
Demolish 40 houses and 6 SPQ, construct and build onsite 216 units in the monument camp facilities, each unit having its own bathroom and shower amenities.
Project Challenges:
This project was located in a remote community/township approximately 10 hours west of the east coast of Northern Australia.
During this project Core managed severe wind and wet weather events and many lightning storms resulting to a delay in the works and schedule.
Project Delivery
With over 130,000 personal hours on this project core successfully delivered this project with zero harm taking away the 2013 work safe awards for Queensland Core Developments delivered a high quality product fully furnished, achieving no loss time and medical treated injury during the construction and demolition periods.