  • DEMOLITION OF 50 HOUSES

    (Quick Facts)

    Project Name: Phosphate Hill Camp Upgrade

    Project Location: Phosphate Hill (50 Houses)

    Project Cost: approx. $1,310,000

    Date of Completion: April 2013

    Duration: 12 Months

    Read more

    IPL PHOSPHATE HILL CAMP UPGRADE

     

    IPL Mine Camp Upgrade Project

     

    (Quick Facts)
    Project Name: Camp upgrade IPL 216 Units
    Project Location: The Monument Camp (Phosphate Hill)
    Project Cost: 15.7M
    Date of Completion: June 2013
    Duration: 14 Months

    Project Scope:

    Demolish 40 houses and 6 SPQ, construct and build onsite 216 units in the monument camp facilities, each unit having its own bathroom and shower amenities.

    Project Challenges:

    This project was located in a remote community/township approximately 10 hours west of the east coast of Northern Australia.

    During this project Core managed severe wind and wet weather events and many lightning storms resulting to a delay in the works and schedule.

    Project Delivery

    With over 130,000 personal hours on this project core successfully delivered this project with zero harm taking away the 2013 work safe awards for Queensland Core Developments delivered a high quality product fully furnished, achieving no loss time and medical treated injury during the construction and demolition periods.

    Read more

    MOUNT CARLTON ELECTRICAL SUBSTATION

    Ergon Substation

    (Quick Facts)
    Project Name: MOUNT CARLTON ELECTRICAL SUBSTATION CIVIL WORKS
    Project Location: Mount Carlton Evolution Mining
    Project Cost: $450,000
    Date of Completion: Nov 2012
    Duration: 16 Weeks

     

    Read more