AMENITIES UPGRADE PROJECT

Project Name: Amenities Upgrade Project
Project Location: Townsville Airport – Domestic Terminal
Date of Completion: Nov 2022
Project Duration: 4 Months
Project Scope: Design and construction of new Amenities female, male, PWD, Parents Room and a certified changing place facility adult changing facility

Project Challenges:

­High level project staging and planning
­Maintaining an operational environment for continued passenger movement ­through the terminal whilst coordinating construction elements in order to meet the client desired completion targets.

Read more

2019 Flood Recovery Works

Oonoonba State School
Heatley Secondary College
Mundingburra primary School
Wulgaru Primary School
Various Commercial and Residential properties in the region
Read more

EDUCATION

Aitkenvale State School (New Covered Link) March 2018
Pimlico State High School (Block F Refurbishment Upper and Lower) June 2018
Pimlico State High School (A Block Alterations) Jan 2020
Heatley State School (Block L Refurbishment Works) May 2018
Hermit Park State School (A Block Refurbishment) May 2019
Bohlevale State School (Block D Upgrade) Nov 2019
Heatley Secondary College (2018 Floods)
Mundingburra State School (2018 Floods)
Wulguru State School (2018 Floods)
Oonoonba State School (2018 Floods)
Read more

HEATLEY STATE SCHOOL BLOCK L

Project Name: Heatley State School Refurbishment of teaching block L
Project Location:  Heatley, QLD, 4814
Project Cost: $380,000.00
Date of Completion: 18/07/2018
Project Duration: 11 weeks
Project Scope: Complete fit out and refurbishment of existing teaching block L
Project challenges: Working in with the school to control a safe and secure construction site during active school hours and have this project completed by the start of a new school term.
Read more